316. The assumption in PERT is A. A project is always behind schedule B. Cost of project is always more than the estimated cost C. A project can be sub-divided into a set of predictable, independent activities D. Activities are complex in nature and time taken by them are indeterminate E. None of the above
316. The assumption in PERT is A. A project is always behind schedule B. Cost of project is always more than the estimated cost C. A project can be sub-divided into a set of predictable, independent activities D. Activities are complex in nature and time taken by them are indeterminate E. None of the above