A power system has a maximum load of 15 MW. Annual load factor is 50%. The reserve capacity of plant is _____ if the plant capacity factor is 40%. a) 3.75 MW b) 7.75 MW c) 46.75 MW d) 8.75 MW
A power system has a maximum load of 15 MW. Annual load factor is 50%. The reserve capacity of plant is _____ if the plant capacity factor is 40%. a) 3.75 MW b) 7.75 MW c) 46.75 MW d) 8.75 MW
Share
Answer: a
Explanation: LF = (Average Demand)/(Maximum Demand)=0.5
Plant capacity factor =(Average Load)/(Plant Capacity)= 0.5/0.4
Plant capacity= (0.5/0.4)*15 = 18.75 MW
Reserve Capacity = 18.75-15 = 3.75 MW.
a) 3.75 MW
Answer: a
a) 3.75 MW
Answer: a
Explanation: LF = (Average Demand)/(Maximum Demand)=0.5
Plant capacity factor =(Average Load)/(Plant Capacity)= 0.5/0.4
Plant capacity= (0.5/0.4)*15 = 18.75 MW
Reserve Capacity = 18.75-15 = 3.75 MW
Answer: a
Explanation: LF = (Average Demand)/(Maximum Demand)=0.5
Plant capacity factor =(Average Load)/(Plant Capacity)= 0.5/0.4
Plant capacity= (0.5/0.4)*15 = 18.75 MW
Reserve Capacity = 18.75-15 = 3.75 MW.