Power plants to be employed as base load plants are not required to have ___________ a) Capability of working continuously b) Low operating cost c) Capability of quick start d) Economical and speedy repair Answer: c Explanation: Capability of quick start is the essential requirement for peak load plant. Base load plants are started once and operated for long time so capability of quick start is not an essential requirement for base load plants.
Power plants to be employed as base load plants are not required to have ___________ a) Capability of working continuously b) Low operating cost c) Capability of quick start d) Economical and speedy repair Answer: c Explanation: Capability of quick start is the essential requirement for peak load plant. Base load plants are started once and operated for long time so capability of quick start is not an essential requirement for base load plants.