1. | In which of the following stages contract documents are prepared? |
A. | Planning stage |
B. | Briefing stage |
C. | Construction stage |
D. | None of the above |
Answer» D. None of the above |
2. | In which of the following stages specifications are prepared? |
A. | Planning stage |
B. | Briefing stage |
C. | Construction stage |
D. | None of the above |
Answer» A. Planning stage |
3. | In which of the following stages practicability of project is ensured? |
A. | Planning stage |
B. | Briefing stage |
C. | Construction stage |
D. | None of the above |
Answer» B. Briefing stage |
4. | Which of the following is not role of contractor |
A. | To arrange land |
B. | To provide resources as per condition of contract |
C. | To work as per plans and specifications |
D. | To put RA and final bill and bill for extra item |
Answer» A. To arrange land |
5. | Which of the following is not role of owner |
A. | To arrange fund |
B. | To arrange land |
C. | To ensure quality of construction |
D. | To arrange necessary approvals |
Answer» C. To ensure quality of construction |
6. | Which of the following organization is widely used in PWD |
A. | Matrix organization |
B. | Line or military organization |
C. | Line and staff organization |
D. | Functional organization |
Answer» C. Line and staff organization |
7. | Which of the following is/are disadvantage/s of Line and Staff organization? |
A. | Experts may not have authority to work properly. |
B. | Conflict between line and staff persons |
C. | Increase in overhead cost due to high salary of staff |
D. | All of the Above |
Answer» D. All of the Above |
8. | In which of the following organization expert advice is available? |
A. | Matrix organization |
B. | Line or military organization |
C. | Line and staff organization |
D. | Functional organization |
Answer» C. Line and staff organization |
9. | Which organization permits quick decision? |
A. | Matrix organization |
B. | Line or military organization |
C. | Line and staff organization |
D. | none |
Answer» B. Line or military organization |
10. | Which of the following is not a characteristics of a Good organization? |
A. | It must have an organization goal |
B. | It should have proper structure |
C. | It should be as big as possible |
D. | It should include all the activities without repeation |
Answer» C. It should be as big as possible |
11. | Road is the example of |
A. | Building constructions. |
B. | Infrastructure construction. |
C. | Industrial construction. |
D. | Special purpose projects |
Answer» B. Infrastructure construction. |
12. | What is the simplest and oldest type of organization? |
A. | Matrix organization |
B. | Line or military organization |
C. | Line and staff organization |
D. | Functional organization |
Answer» B. Line or military organization |
13. | What is Span of management? |
A. | It is the number of persons to be supervised by a manager |
B. | It is the number of years for management to remain active |
C. | It is the average age of manager in a business |
D. | It is the number of achievements of management |
Answer» A. It is the number of persons to be supervised by a manager |
14. | What is organization? |
A. | Arrangement of persons in business |
B. | Arrangement of machines on site |
C. | Arrangement of money for business |
D. | Arrangement of materials at site |
Answer» A. Arrangement of persons in business |
15. | What is 4M of construction? |
A. | 4 types of organizations |
B. | 4 resources for construction |
C. | 4 types of construction managers |
D. | 4 types of construction managers |
Answer» B. 4 resources for construction |
16. | In which type of tender advantage of keen bidding competition can be availed. |
A. | Open tender or public tender |
B. | Selected tender |
C. | Negotiated tender |
D. | None of the above |
Answer» A. Open tender or public tender |
17. | What SMB stands for? |
A. | Short measurement book |
B. | Salient measurement book |
C. | Standard measurement book |
D. | None of the above |
Answer» C. Standard measurement book |
18. | SD, mobilization advance and cost of materials given to contractor will be deducted from |
A. | RA bill |
B. | Final bill |
C. | EMD |
D. | None of the above |
Answer» A. RA bill |
19. | What EMD stands for? |
A. | Exact money deposit |
B. | Earnest money deposit |
C. | Exact money deduction |
D. | Exact monthly deduction |
Answer» B. Earnest money deposit |
20. | Which of the following contract is most suitable for road and bridges? |
A. | BOT contract |
B. | Cost plus fixed fee contract |
C. | All in one contract |
D. | Labour contract |
Answer» A. BOT contract |
21. | In which of the following contract; contractor tries to complete job quickly? |
A. | Item rate contract |
B. | Cost plus fixed fee contract |
C. | All in one contract |
D. | Labour contract |
Answer» B. Cost plus fixed fee contract |
22. | In which of the following contract; contractor is quickly be agreed and work on job? |
A. | Cost plus percentage rate contract |
B. | Lump sum contract |
C. | Piece work agreement |
D. | Labour contract |
Answer» A. Cost plus percentage rate contract |
23. | In which of the following contract; contractor is not required to deposit SD? |
A. | Item rate contract |
B. | Lump sum contract |
C. | Piece work agreement |
D. | Labour contract |
Answer» C. Piece work agreement |
24. | In which of the following contract; contractor is required to offer a fixed sum for job in all respect as per given drawings and details? |
A. | Item rate contract |
B. | Lump-sum contract |
C. | All in one contract |
D. | Labor contract |
Answer» B. Lump-sum contract |
25. | Extra items will cause headache in item rate contract |
A. | Right |
B. | Wrong |
C. | none |
D. | all |
Answer» A. Right |
26. | Which of the following is/are advantages of item rate contract |
A. | Elasticity and fair to both the parties |
B. | Economical |
C. | Absence of uncertainties |
D. | All of the above |
Answer» D. All of the above |
27. | Specialized work needs departmental execution |
A. | Right |
B. | Wrong |
C. | none |
D. | all |
Answer» B. Wrong |
28. | Contract system is suitable for big projects |
A. | Right |
B. | Wrong |
C. | none |
D. | all |
Answer» A. Right |
29. | Departmental execution is suitable for small jobs |
A. | Right |
B. | Wrong |
C. | none |
D. | all |
Answer» A. Right |
30. | Which of the following is not essential requirement for contract |
A. | Parties must be competent |
B. | Should be made by free consent |
C. | There shall be definite and legal proposal and its acceptance. |
D. | Both Parties must be citizens of same country |
Answer» D. Both Parties must be citizens of same country |
31. | PERT requires |
A. | Single time estimate |
B. | Probable time estimate |
C. | Triple time estimate |
D. | None of the above |
Answer» C. Triple time estimate |
32. | CPM requires |
A. | Single time estimate |
B. | Probable time estimate |
C. | Triple time estimate |
D. | None of the above |
Answer» A. Single time estimate |
33. | CPM stands for |
A. | Combined process method |
B. | Critical path method |
C. | Construction planning method |
D. | Continuous progress method |
Answer» B. Critical path method |
34. | CPM is |
A. | Event oriented |
B. | Activity oriented |
C. | Mostly event oriented |
D. | Mostly activity oriented |
Answer» B. Activity oriented |
35. | PERT is |
A. | Event oriented |
B. | Activity oriented |
C. | Mostly event oriented |
D. | Mostly activity oriented |
Answer» A. Event oriented |
36. | An activity is represented by |
A. | An arrow |
B. | Circle |
C. | Triangle |
D. | None of the above |
Answer» A. An arrow |
37. | An activity requires |
A. | Events |
B. | Time and resources |
C. | Resources |
D. | Energy |
Answer» B. Time and resources |
38. | Actual performance of a task is known as |
A. | An event |
B. | An activity |
C. | A duration |
D. | None of the above |
Answer» B. An activity |
39. | PERT stands for |
A. | Programme estimation and reporting techniques |
B. | Process estimation and review techniques |
C. | Programme evaluation and review techniques |
D. | Planning estimating and result techniques |
Answer» C. Programme evaluation and review techniques |
40. | The earliest method of project planning was |
A. | CPM |
B. | PERT |
C. | Bar chart |
D. | Mile stone chart |
Answer» C. Bar chart |
41. | A drawback of bar chart is that |
A. | All the activities are independent |
B. | It is difficult to know whether activity is completed or not |
C. | The sequence of activity is not clearly defined |
D. | All of the above |
Answer» C. The sequence of activity is not clearly defined |
42. | A bar chart is drawn for |
A. | Time versus activity |
B. | Activity versus resources |
C. | Resources versus progress |
D. | Progress versus time |
Answer» A. Time versus activity |
43. | Bar chart is also known as |
A. | Flow chart |
B. | Time chart |
C. | Travel chart |
D. | Gantt chart |
Answer» D. Gantt chart |
44. | Bar chart is very popular because |
A. | It is very simple |
B. | Each activity is shown separately |
C. | Modification is easy |
D. | All of the above |
Answer» A. It is very simple |
45. | Bar chart is suitable for |
A. | Large project |
B. | Major work |
C. | Minor work |
D. | All of these |
Answer» C. Minor work |
46. | Economic cost is the only reason for which a contractor should be conscious of construction safety. |
A. | TRUE |
B. | FALSE |
C. | none |
D. | all |
Answer» B. FALSE |
47. | The construction industry has accounted for about ………% of all occupational injuries |
A. | 20 |
B. | 25 |
C. | 11 |
D. | 5 |
Answer» C. 11 |
48. | Carelessness is the cause of an accident that can be attributed to |
A. | Planning, organization |
B. | Execution of work |
C. | Management |
D. | None of the above |
Answer» D. None of the above |
49. | Which of the following cause of an accident can be attributed to organization? |
A. | Use of unsuitable material |
B. | Defective supervision of work |
C. | Unsuitable equipment |
D. | Unskilled operators |
Answer» B. Defective supervision of work |
50. | There are as many possible causes of accidents as there are occasions |
A. | TRUE |
B. | FALSE |
C. | none |
D. | all |
Answer» A. TRUE |
51. | Who should be allowed to go below slab when centering is in position and concreting of slab is going on |
A. | Only head carpenter |
B. | Every worker |
C. | Nobody |
D. | Only safety officer |
Answer» C. Nobody |
52. | In case of cantilever beam, reinforcement must be placed at the ……. of the member. |
A. | Top |
B. | Bottom |
C. | Sides |
D. | None of the above |
Answer» A. Top |
53. | Full width of road should be taken for bituminous work at a time so that job is completed in time. |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» B. Disagree |
54. | Pile drivers should be kept near electricity line to get electricity |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» B. Disagree |
55. | Before starting piling work, a complete knowledge of underground structures (such as sewers, water pipeline, gas mains etc.) is essential. |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» A. Agree |
56. | If work of piling is to be carried out at night, minimum……….. ‘lux luminance lights should be used. |
A. | 60 |
B. | 200 |
C. | 150 |
D. | 100 |
Answer» D. 100 |
57. | Moving parts of all equipment should be |
A. | Removed |
B. | Provided with safety guards. |
C. | Replaced with stationary parts |
D. | None of the above |
Answer» B. Provided with safety guards. |
58. | Heavy equipment, such as excavating machinery, trucks, dumpers, etc. should be kept away from the excavated sides at a distance not less than the depth of trench |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» A. Agree |
59. | Excavated material should be kept nearby from the edge of the trench |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» B. Disagree |
60. | Whenever workmen have to excavate in trenches in soil, soft rock or hard soil exceeding …………. m in depth, the trenches should be securely shored and timbered. |
A. | 2 |
B. | 1.5 |
C. | 3 |
D. | 2.1 |
Answer» A. 2 |
61. | Outputs of management control level is |
A. | Goals and policies |
B. | Actions |
C. | Decisions and personal leadership |
D. | None of the above |
Answer» C. Decisions and personal leadership |
62. | Special one time reports are information system used by |
A. | Head of department |
B. | Top management |
C. | Supervisor,foreman,clerk |
D. | None of the above |
Answer» B. Top management |
63. | Formal reports are information system used by |
A. | Head of department |
B. | Top management |
C. | Supervisor,foreman,clerk |
D. | None of the above |
Answer» C. Supervisor,foreman,clerk |
64. | Operational control is responsibility of |
A. | Head of department |
B. | Top management |
C. | Supervisor,foreman,clerk |
D. | MIS |
Answer» C. Supervisor,foreman,clerk |
65. | Strategic Planning is responsibility of |
A. | Head of department |
B. | Top management |
C. | Supervisor |
D. | MIS |
Answer» B. Top management |
66. | Which of the following is not a components of the system. |
A. | Inputs |
B. | Outputs |
C. | Processing devices |
D. | Decision making |
Answer» D. Decision making |
67. | System means |
A. | Group of various units |
B. | Team of clever people |
C. | Method of construction |
D. | Goal of organization |
Answer» A. Group of various units |
68. | Management consists of ……………………………. levels. |
A. | Top and bottom level |
B. | Higher and lower level |
C. | Three levels-top level, middle level and lower level. |
D. | Six |
Answer» C. Three levels-top level, middle level and lower level. |
69. | ………………….. is an important element of group activities. |
A. | Management |
B. | Construction team |
C. | Team effort |
D. | None of the above |
Answer» A. Management |
70. | The main function of MIS is to deal with government |
A. | Right |
B. | Wrong |
C. | none |
D. | all |
Answer» B. Wrong |
71. | Negative attitude can be controlled by |
A. | Religion |
B. | Values |
C. | Introduction of strict disciplined environment |
D. | None of the above |
Answer» B. Values |
72. | Care for male employees and justice for female and child worker can create positive attitude |
A. | Right |
B. | Wrong |
C. | none |
D. | all |
Answer» B. Wrong |
73. | Positive, warm and committed attitude enhances |
A. | Project duration |
B. | Team effort |
C. | Attitude |
D. | Nature |
Answer» B. Team effort |
74. | ………………… is a function of values and perception of a person |
A. | Success |
B. | Relation |
C. | Attitude |
D. | Nature |
Answer» C. Attitude |
75. | Person selects information that suits his |
A. | Religion |
B. | Values |
C. | Embitions |
D. | Environment |
Answer» B. Values |
76. | Employees having their age more than…………..years can become the members of the union. |
A. | 18 |
B. | 15 |
C. | 21 |
D. | 25 |
Answer» B. 15 |
77. | The first Trade union Act in India was passed in |
A. | 1926 |
B. | 1942 |
C. | 1920 |
D. | 1914 |
Answer» A. 1926 |
78. | CITU stands for |
A. | Centre of Industrial Trade Union |
B. | Centre of Innovative Trade Union |
C. | Centre of Indian Trade Union |
D. | None of the above |
Answer» C. Centre of Indian Trade Union |
79. | Trade unions are voluntary organisations formed by laborers to protect their interest |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» A. Agree |
80. | Economical aspects of labour welfare includes |
A. | High wages, bonus, medical aid, |
B. | Educational facilities, training, reading room, club |
C. | Transportation |
D. | None of the above |
Answer» A. High wages, bonus, medical aid, |
81. | Better working conditions |
A. | Direct financial incentive |
B. | Non financial incentive |
C. | Indirect financial incentive |
D. | None of the above |
Answer» B. Non financial incentive |
82. | Attendance bonus |
A. | Direct financial incentive |
B. | Non financial incentive |
C. | Indirect financial incentive |
D. | None of the above |
Answer» A. Direct financial incentive |
83. | Meritorious service awards is |
A. | Direct financial incentive |
B. | Non financial incentive |
C. | Indirect financial incentive |
D. | None of the above |
Answer» B. Non financial incentive |
84. | Gratuity is |
A. | Direct financial incentive |
B. | Non financial incentive |
C. | Indirect financial incentive |
D. | None of the above |
Answer» C. Indirect financial incentive |
85. | Profit sharing bonus |
A. | Direct financial incentive |
B. | Non financial incentive |
C. | Indirect financial incentive |
D. | None of the above |
Answer» A. Direct financial incentive |
86. | Leave encashment is |
A. | Direct financial incentive |
B. | Non financial incentive |
C. | Indirect financial incentive |
D. | None of the above |
Answer» C. Indirect financial incentive |
87. | Wages of worker is liability of |
A. | Engineer |
B. | Government |
C. | Employer |
D. | NGO |
Answer» C. Employer |
88. | Labor is perishable resource |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» A. Agree |
89. | The stack height for flooring tiles should not be more than…….. m. |
A. | 1.5 |
B. | 2.0 |
C. | 1.0 |
D. | 1.75 |
Answer» C. 1.0 |
90. | The stack height for bricks should not be more than ………. m. |
A. | 1.2 |
B. | 1.5 |
C. | 1.75 |
D. | 2.0 |
Answer» B. 1.5 |
91. | Tests for performance of construction is done in |
A. | Planning stage |
B. | Briefing stage |
C. | Construction stage |
D. | Commissioning stage |
Answer» D. Commissioning stage |
92. | Which of the following are the qualities of good construction manager? |
A. | Good character. |
B. | Integrity to enhance teamwork. |
C. | Devotion to duty. |
D. | All of the above |
Answer» D. All of the above |
93. | The main function of the construction management is |
A. | Organizing |
B. | Directing |
C. | Planning |
D. | All of the above |
Answer» D. All of the above |
94. | The construction of residential building are treated as |
A. | light construction |
B. | heavy construction |
C. | industrial construction |
D. | none of these |
Answer» A. light construction |
95. | The construction of airports are treated as |
A. | light construction |
B. | heavy construction |
C. | industrial construction |
D. | none of these |
Answer» B. heavy construction |
96. | A construction team includes |
A. | owner |
B. | engineer |
C. | architect |
D. | all of these |
Answer» D. all of these |
97. | The field of activities of an engineer includes |
A. | estimation |
B. | approval of construction plans by the local authority |
C. | inspection and payment of work done by contractor |
D. | all of above |
Answer» D. all of above |
98. | F.W. Taylor introduced a system of organization known as |
A. | line and staff organization |
B. | line organization |
C. | functional organization |
D. | none of these |
Answer» C. functional organization |
99. | In a functional organization |
A. | quality of work is better |
B. | specialized knowledge and guidance to individual worker is provided |
C. | wastage of material is minimum |
D. | all of the above |
Answer» D. all of the above |
100. | The major principle of an organization is |
A. | span of management |
B. | unity of command |
C. | delegation of authority |
D. | all of these |
Answer» D. all of these |
101. | The notice inviting tender should published in minimum…….. daily news paper |
A. | 3 |
B. | 2 |
C. | 4 |
D. | 5 |
Answer» B. 2 |
102. | Who will sign the contract deed on behalf of government |
A. | Chief engineer |
B. | Superintendent engineer |
C. | Executive engineer |
D. | Head clerk |
Answer» C. Executive engineer |
103. | Who will draft contract agreement? |
A. | Chief engineer |
B. | Divisional head clerk |
C. | Executive engineer |
D. | None of the above |
Answer» B. Divisional head clerk |
104. | Which are the criteria to be checked for pre- qualification of contractor |
A. | Financial strength |
B. | Past five year experience |
C. | Technical personnel engaged |
D. | All of the above |
Answer» D. All of the above |
105. | How many envelops are required to submitted Tender form |
A. | 3 |
B. | 1 |
C. | 4 |
D. | 2 |
Answer» C. 4 |
106. | Total no of grades for registration of contractor with governments are |
A. | 3 |
B. | 5 |
C. | 7 |
D. | 4 |
Answer» C. 7 |
107. | Contract is terminated in case of |
A. | Slow progress and time limit exceeds |
B. | Work is not being executed as per specifications and instruction of EIC |
C. | Contractor tries to admit sub-contractor |
D. | All of the above |
Answer» D. All of the above |
108. | Form no ………is used for material at site account |
A. | 35 |
B. | 28 |
C. | 16 |
D. | 9 |
Answer» A. 35 |
109. | Mobilization advance |
A. | Shall be 2 to 5 % of project cost. |
B. | Shall be 3 to 7 % of project cost. |
C. | Shall be 10 to 15 % of project cost. |
D. | Shall be 12 to 18 % of project cost. |
Answer» A. Shall be 2 to 5 % of project cost. |
110. | Stock account is cleared yearly while tools and plants account is cleared half yearly |
A. | TRUE |
B. | FALSE |
C. | none |
D. | all |
Answer» B. FALSE |
111. | PERT analysis is based upon |
A. | Optimistic time |
B. | Pessimistic time |
C. | Most likely time |
D. | All of the above |
Answer» D. All of the above |
112. | The time activity consumes in most adverse conditions is |
A. | Optimistic time |
B. | Pessimistic time |
C. | Most likely time |
D. | All of the above |
Answer» B. Pessimistic time |
113. | The time activity consumes in normal conditions is |
A. | Optimistic time |
B. | Pessimistic time |
C. | Most likely time |
D. | All of the above |
Answer» C. Most likely time |
114. | The difference between the total float and free float is called |
A. | Duration |
B. | Interfering float |
C. | Critical activity |
D. | None of the above |
Answer» B. Interfering float |
115. | The critical path is |
A. | The longest path of the network |
B. | The shortest path of the network |
C. | The average duration path of the network |
D. | None of the above |
Answer» A. The longest path of the network |
116. | The float of critical activity is always |
A. | Maximum |
B. | Minimum |
C. | Zero |
D. | None of the above |
Answer» C. Zero |
117. | A dummy activity in a network |
A. | Is represented by dotted line |
B. | Is an artificial activity |
C. | Does not consume time and resources |
D. | All of the above |
Answer» D. All of the above |
118. | Activity starts from |
A. | Head event |
B. | Tail event |
C. | Dual role event |
D. | None of the above |
Answer» B. Tail event |
119. | Which of the following is an activity |
A. | Excavation |
B. | Curing |
C. | Laying concrete |
D. | All of the above |
Answer» D. All of the above |
120. | Earliest start time of activity equals to |
A. | TE of tail event of an activity |
B. | TE of head event of an activity |
C. | Average time of TE of tail event and head event |
D. | None of the above |
Answer» A. TE of tail event of an activity |
121. | …………….is provided to safeguard scaffolding against overturning. |
A. | Standards |
B. | Inclined rackers |
C. | Put-logs |
D. | Rails |
Answer» B. Inclined rackers |
122. | Ladder leading to landing should be extended at least ……. meter above the landing |
A. | 1.2 |
B. | 1.5 |
C. | 1 |
D. | 1.8 |
Answer» C. 1 |
123. | While using ladder one should not lean sideways more than……… cms. |
A. | 40 |
B. | 60 |
C. | 30 |
D. | 45 |
Answer» C. 30 |
124. | Wooden ladders should be inspected at least……….. a month. |
A. | Once |
B. | Twice |
C. | Three times |
D. | Four times |
Answer» A. Once |
125. | In sheds for ceiling works, ……………………. scaffolding is economical. |
A. | Suspended |
B. | Needle |
C. | Ordinary |
D. | None of the above |
Answer» A. Suspended |
126. | The construction industry has accounted for about …………% of all deaths due to accident at place of work |
A. | 5 |
B. | 20 |
C. | 25 |
D. | 30 |
Answer» B. 20 |
127. | For repair works at high level of multistoreyed buildings needle scaffolding is preferred |
A. | As it is more stable |
B. | As it looks better |
C. | As it will not obstruct traffic at ground level. |
D. | None of the above |
Answer» C. As it will not obstruct traffic at ground level. |
128. | PPE stands for |
A. | Personal protective equipment |
B. | Preferred protective equipment |
C. | Prohibited protective equipment |
D. | None of the above |
Answer» A. Personal protective equipment |
129. | For work at height one should use |
A. | Safety belt |
B. | Full body harness |
C. | none |
D. | all |
Answer» B. Full body harness |
130. | A good safety record can produce higher morale, productivity and stronger employee loyalty. |
A. | Right |
B. | Wrong |
C. | none |
D. | all |
Answer» A. Right |
131. | Who plays a crucial role in convincing the operating staff to adopt the change? |
A. | HRD manager |
B. | Junior engineer |
C. | Public relation officer |
D. | Supervisor |
Answer» D. Supervisor |
132. | Supervisor is at the lowest level of management |
A. | Right |
B. | Wrong |
C. | none |
D. | all |
Answer» A. Right |
133. | …………. has 3 roles ;Trainer,Motivator and Facilitator |
A. | HRD manager |
B. | Junior engineer |
C. | Public relation officer |
D. | Supervisor |
Answer» D. Supervisor |
134. | HRD is mainly concerned with |
A. | Optimum stress |
B. | Optimum cost |
C. | Optimum duration |
D. | None of the above |
Answer» A. Optimum stress |
135. | Which one of the following is not a system of HRD |
A. | Optimization of resources system |
B. | Appraisal system |
C. | Carrier system |
D. | Training System |
Answer» A. Optimization of resources system |
136. | Human resource is a |
A. | Perishable resource |
B. | Dynamic resource |
C. | Both A and B |
D. | None of the above |
Answer» C. Both A and B |
137. | Human resource development (HRD) is a |
A. | Process |
B. | Previlege |
C. | Business cycle |
D. | None of the above |
Answer» A. Process |
138. | HRD is a process which progresses by |
A. | Proper management of resource |
B. | customer satisfaction |
C. | Time resource optimization |
D. | Performance appraisal,Counseling and training |
Answer» D. Performance appraisal,Counseling and training |
139. | MIS stands for |
A. | Management Innovation System |
B. | Management Information System |
C. | Management Interaction style |
D. | None of the above |
Answer» B. Management Information System |
140. | HRD stands for |
A. | Human resource development |
B. | Human resource design |
C. | Higher resource development |
D. | None of the above |
Answer» A. Human resource development |
141. | In one stack not more than………. cement bags should be stored one above other. |
A. | 8 |
B. | 10 |
C. | 15 |
D. | 12 |
Answer» D. 12 |
142. | The space between the walls and cement bags all-round should be at least……… cms. |
A. | 30 |
B. | 50 |
C. | 60 |
D. | 40 |
Answer» A. 30 |
143. | EOQ stands for |
A. | Equal order quantity |
B. | Economic order quantity |
C. | Extra order quantity |
D. | None of the above |
Answer» B. Economic order quantity |
144. | Timber and plywood should be stacked separately. |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» A. Agree |
145. | In any construction project the material cost constitute about….. % of the total project cost. |
A. | 60 |
B. | 25 |
C. | 35 |
D. | 45 |
Answer» A. 60 |
146. | While placing of concrete, it should not be dropped from more than …….m height. |
A. | 2 |
B. | 1 |
C. | 3 |
D. | 4 |
Answer» B. 1 |
147. | The coarse aggregates of different sizes like 5 to 10 mm, 10 to 20 mm, 20 to 40 mm etc. should be stored in different piles. |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» A. Agree |
148. | Which of the following is not a principle of preparing job layout |
A. | Location of auditorium |
B. | Administrative block |
C. | Warehouses/godown |
D. | Entry and Exit |
Answer» A. Location of auditorium |
149. | Which of the following is not a purpose of making job layout |
A. | To develop human resources in organization |
B. | To save time of delivery of material |
C. | To safeguard material from wastage and theft |
D. | To keep lead minimum |
Answer» A. To develop human resources in organization |